Mailand-Crestview Forest Area Street Improvements

Mailand-Crestview Forest Area Pavement Rehabilitation, City Project 18-27, is a pavement rehabilitation project constructed in 2019. The project included many different improvements to the neighborhood street and utility infrastructure including the installation of new pavement, the full depth reclamation (grinding) of existing pavement and underlying aggregate base, the spot replacement of deteriorated concrete curb and gutter, and upgrades to the storm sewer system.

Project Status

The Mailand-Crestview Forest Area Improvements have been completed. City Staff will inspect the project area in 2020 for any necessary repairs. These repairs would be completed under the Contractor’s warranty. Area residents will be notified in advance if it is anticipated that any warranty repairs would cause a major disruption. 

Target Date Actions
February 11, 2019 Accept Feasibility Study, Order Public Hearing, Authorize Preparation of Plans of Specifications
February 25, 2019 Public Hearing and Order Improvement
April 8, 2019 Approve Plans and Specifications, Authorize Advertisement for Bids, Authorize Preparation of Assessment Roll
April 22, 2019 Accept Assessment Roll & Order Assessment Hearings
May 9, 2019 Bid Opening 
May 13, 2019 Assessment Hearing, Award Contract
June 10, 2019 Adopt Revised Assessment Roll
June 2019 Begin Construction
November 2019 Assessments Certified to Ramsey County
November 2019 Construction Completed